Given that we were in the process of restoring our back deck what better time than now to install an awesome water feature.
Determine layoutOn this deck all existing structure was maintained we simply redid the top deck boards post and rails. This little corner angle happened to be the perfect location for what I had in mind.
Test fit Using a 4ft water trough I positioned between the two post to make sure it would fit as intended without taking up too much deck space. This sizing was perfect.
Making bracesUsing a 2×6 I cut to the width between the two post. I laid the 2×6 on top of the post carefully aligning and marked the angles. Using a jigsaw I cut out each corner this allowed the brace to slide tightly between each post. I then made 2 additional exactly the same.
Drilling for plumbingWith the first brace in place I held the spillway in place to make sure the inlet fell in the center. Knowing the size of the tubing I then drilled a 1 1/2 inch hole.